How Timor-Leste's internet connectivity depends on submarine cables

Geography and Connectivity Nodes
Timor-Leste, a small island nation in Southeast Asia, has limited internet connectivity through submarine cables. The only cable landing point is located in the capital, Dili, making the country vulnerable to disruptions. In the coming years, two cables are planned for connection: Asia Connect Cable-1 (ACC-1) and Hawaiki Nui 1. The length of ACC-1 will be 19,000 kilometers, while Hawaiki Nui 1 will span 10,000 kilometers. They are expected to become operational in 2027-2028. While these projects are still in the planning stage, internet connectivity in the country is provided only through satellite channels and terrestrial networks, which is reflected in a low connectivity resilience index (33 out of 100).
Internet Regime and Control
According to GeoCables, there is no evidence of active use of digital censorship in Timor-Leste, as direct measurements of DNS filtering or other control methods have not been conducted. However, the internet is regulated by national legislation, as in most countries. Due to limited infrastructure and a single landing point, the state theoretically has the ability to control internet traffic. Currently, there is no confirmation of large-scale censorship.
Conflicts and Their Impact
The history of Timor-Leste includes periods of political instability and conflicts, which have affected the development of infrastructure, including the internet. Since gaining independence in 2002, the country has faced challenges in building a reliable telecommunications network. So far, the impact of these events on submarine cables has been minimal, as their connection is only in the planning stages. However, in the event of future conflicts, the single landing point in Dili could become vulnerable to damage or disruptions.
Bottlenecks and Risks
The main risk for internet connectivity in Timor-Leste is the reliance on a single landing point in Dili and the lack of backup routes. Any cable damage or blockage of access to this node could completely isolate the country. Neighboring countries, such as Indonesia and Australia, serve as transit nodes for future cable routes, but their connection to Timor-Leste is also limited. Delays in connecting the ACC-1 and Hawaiki Nui 1 cables may extend the period of vulnerability.
Monitoring by GeoCables
GeoCables is monitoring the development of the ACC-1 and Hawaiki Nui 1 projects, which are expected to improve internet connectivity in Timor-Leste. These cables will provide international connections through the node in Dili, opening up new opportunities for the country. Our platform will continue to monitor their construction and operation to promptly identify risks and analyze the resilience of the infrastructure. Currently, information about submarine cables in Timor-Leste is limited, but significant changes are expected in the coming years.
| Cable | Length | RFS | RTT now | Baseline | Status |
|---|---|---|---|---|---|
| Asia Connect Cable-1 (ACC-1) | 19,000 km | 2028 | 180 ms | - | nominal |
| Hawaiki Nui 1 | 10,000 km | 2027 | - | - | nominal |