SeaMeWe-5: damage off Pakistan's coast, repair by 6 Dec
GeoCables, based on reports from PTA and Transworld Associates
On 18 November the SeaMeWe-5 subsea cable was damaged off the coast of Pakistan, and internet in the country slowed noticeably. According to Transworld Associates (24NewsHD), repairs are due to finish by 6 December.
What happened
The fault was found about 11 kilometres from the shore. On 18 November the Pakistan Telecommunication Authority (PTA) linked it to slow internet and dropped connections for many users across the country.
SeaMeWe-5 has been in service since 2016 and is 20,000 kilometres long. It is owned by a consortium of operators; in Pakistan it is represented by Transworld Associates.
Until the cable is repaired, traffic is carried over other links, but connections remain slower than usual. Transworld Associates is working with the consortium to find the cause of the damage. According to the company (24NewsHD), repairs are due to finish by 6 December.
Since 14 November the cable ship CS Maram has been working off Karachi, where several subsea cables come ashore, according to navigational warnings NAVAREA IX 440/26 and HYDROPAC 3343/26. On 24 November the work area moved closer to the shore (NAVAREA IX 465/26). The warnings do not say which cable is being repaired.
What we see. According to GeoCables measurements, on 18-19 November latency in 4 of Pakistan’s 9 major networks rose to 236 ms against the usual 135 ms, with packet loss reaching 16%. On the evenings of 20, 21 and 22 November latency rose again, in 7, 5 and 8 of the 9 networks.
What we see
Delay inside Pakistani networks rose from 18 Nov: up to 236 ms against the usual 135 ms, and again on the evenings of 20-22 Nov.
How it unfolded
- 14 Nov 2026 NAVAREA IX 440/26: cable ship CS Maram working off Karachi
- 18 Nov 2026 PTA links internet disruption to SeaMeWe-5 damage
- 18 Nov 2026 GeoCables measurements: latency up in 4 of 9 major networks in Pakistan
- 22 Nov 2026 GeoCables measurements: evening latency up in 8 of 9 networks
- 23 Nov 2026 Transworld Associates: repairs under way, completion by 6 December (24NewsHD)
- 24 Nov 2026 NAVAREA IX 465/26: CS Maram work area moves closer to shore
Sources
Related pages
More on the topic
Details
The Vietnam-Thailand-Singapore (VTS) cable consortium of Viettel, Singtel and AIS signed commercial and construction contracts on 26 November 2026; the cable is due to enter service in the fourth quarter of 2030.
Details
Path changed: Tonga–Fiji traffic is routed via Australia, latency about 7 times higher than usual since 24 Nov; the cable is working and the connection is up.
Details
The EU granted EUR 11.1 million through the European Investment Bank to extend the Medusa cable from its Egyptian landing at Port Said to Jordan.